| BEACH STATUS | Sand scraping from beach to dunes on Thursday, May 31 (finishing Monday June 4) | Dune fence & posts received |
| BEACH ACCESS STATUS |
| Street | Walkway | Stairs | Footwash | Misc |
| East Evergreen | 20' of additional pavers needed | steps in place | valve disabled; sand needs to be shoveled out | - |
| East Addy | usable | steps in place | working; sand needs to be shoveled out | post/rail fencing needed north side |
| Bridge | usable | steps in place | working; sand needs to be shoveled out | post/rail fencing needed south side |
| East Errett | usable | steps in place | NOT working-underground pipe froze over the winter | - |
| East Bayberry | 25' of additional pavers | handicapped access ramp in place | working; sand needs to be shoveled out | post/rail installed south side |